Reconstruction of Water and Sewerage Works in Agstafa

General information about the project

Customer: “Agency for Territorial Rehabilitation of the Republic of Azerbaijan”

Designer: “Ay Consulting” LLC

Contractor: Akkord Industrial Construction Investment Corporation

Type of contract: “Construction Contract”

Contract value: $ 41,708,576

Financing bank: “Azerbaijan State Budget”

Construction start date: 2011

Completion date of construction: 2015

Construction period: 48 months

Number of home speeches: 4441 units

Length of water network: 72 km

Length of sewerage network: 81 km

Sewage wells: 1800 units

Artesian wells: 6 pieces

Depth of artesian wells: 900 m

Reservoirs: 2x2500 m³

Water pumps: 1 unit - 480 m³ / h

CSTQ: 1 device x 4400 m³ / day

Description of the project

6 subartesian wells were drilled for the drinking water supply of Agstafa city, 2 reservoirs with the capacity of 1000 m³ and 1500 m³ were built, 164521.5 m long water network and 139688.0 m long sewerage network were laid. A Wastewater Treatment Plant with a capacity of 4900 m³ / day, an administrative building, a laboratory building, and other ancillary buildings was built and put into operation. With the implementation of this project, it will be possible to provide 28,000 people with drinking water 24 hours a day.

Projects

  • Pipeline
  • Completed

Reconstruction of Water and Sewerage Works in Tovuz City

  • Pipeline
  • Completed

The Trans-Anatolian Natural Gas Pipeline (TANAP)

All rights reserved © 2005-2021.