General information about the project
Customer: - "Road Department of the Ministry of Regional Development and Infrastructure of Georgia"
Designer: - "Road Department of the Ministry of Regional Development and Infrastructure of Georgia"
Contractor: - “Akkord Industrial Construction Investment Corporation” OJSC
Type of contract: - "FIDIC"
The cost of the contract: - 46,430,364.95 GEL
Financing Bank: - “State Budget of the Republic of Georgia”
Construction start date: - 28.12.2018
Completion date of construction: - 28.10.2020
Construction period: - 24 months
The technical level of the road: - Yes
The length of the road: - 16,600 km
Description of the project
Technical parameters of the road on Lot-3:
The technical level of the road - yes
The width of the road is 28.5m
The width of the traffic lane is 3.75 m
The width of the dividing strip - 6m
Width of the carriageway - 2x7.5m (7.5mx2)
The width of the road reinforcement strip - 0.75m (0.75x2m)
Shoulder width of the road - 3m
Artificial devices:
Water pipes: Length of rectangular pipes - 203 m
1.5x2.0-6 pieces
2.5x4.0-9 pieces
6.0x4.5-4 pieces
Bridges:
-
Bridge Pk 21 + 285
+ length - 33 m
+ number of piles - 20
+ number of passes – 6
-
Bridge Pk 29 + 770
+ length - 33 m
+ number of piles - 20
+ number of passes - 6